Power by county
Teton, WY: data center power outlook
The grid around Teton, Wyoming is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Teton the mapped layer shows 16 mapped substations, with grid access reaching 161 kV at its strongest point. Retail service across Teton is split among 6 utilities, among them FALL RIVER RURAL ELEC COOP INC, HIGH PLAINS POWER INC, LOWER VALLEY ENERGY INC.
Grid position at a glance
- Serving utilities
- FALL RIVER RURAL ELEC COOP INC, HIGH PLAINS POWER INC, LOWER VALLEY ENERGY INC, NORTHWESTERN ENERGY LLC - (MT), WAPA-- WESTERN AREA POWER ADMINISTRATION, WILLWOOD LIGHT & POWER COMPANY
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 161 kV
- Substations in county
- 16
- Industrial retail rate
- 8.7¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 6 serving utilities: 5.3 to 8.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 1,410 lb CO2/MWh
- Water withdrawals
- 112 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 11,062 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Teton
Read on for the public power picture of Teton in Wyoming, assembled for data center siting. Transmission-class access reaches 161 kV in Teton at its strongest mapped point. Teton contains 16 mapped substations, a moderate footprint spread across the service area.
There is no organized wholesale market over Teton, Wyoming; arrangements run through the serving utility instead. Teton carries the state industrial average retail rate of 8.7 cents per kWh from EIA-861, applied statewide. For Teton, the per-utility spread is 2 of 6 serving utilities: 5.3 to 8.2¢/kWh, which qualifies but never replaces the state average.
For Teton, Wyoming, no queued project appears in the feeds currently covered. For Teton, Wyoming, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Teton shows 1,410.035 lb CO2 per MWh.
For Teton, the USGS 2015 compilation records 111.52 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Teton sits within commuting range of roughly 11,062 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Teton here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Teton, Wyoming settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Teton, Wyoming requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Teton, Wyoming are logged directly below, so each figure on this page can be traced back to its public dataset.