Power by county
Sublette, WY: data center power outlook
The grid around Sublette, Wyoming is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Sublette the mapped layer shows 8 mapped substations, with grid access reaching 230 kV at its strongest point. Retail service across Sublette is split among 4 utilities, among them BRIDGER VALLEY ELEC ASSN, INC, LOWER VALLEY ENERGY INC, PACIFICORP.
Grid position at a glance
- Serving utilities
- BRIDGER VALLEY ELEC ASSN, INC, LOWER VALLEY ENERGY INC, PACIFICORP, WAPA-- WESTERN AREA POWER ADMINISTRATION
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 230 kV
- Substations in county
- 8
- Industrial retail rate
- 8.7¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 4 serving utilities: 5.3 to 7.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 1,410 lb CO2/MWh
- Water withdrawals
- 658 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 2,592 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Sublette
The sections below set out what public data shows about siting a large electrical load in Sublette, Wyoming. Transmission-class access reaches 230 kV in Sublette at its strongest mapped point. Sublette contains 8 mapped substations, a moderate footprint spread across the service area.
There is no organized wholesale market over Sublette, Wyoming; arrangements run through the serving utility instead. Sublette carries the state industrial average retail rate of 8.7 cents per kWh from EIA-861, applied statewide. For Sublette, the per-utility spread is 2 of 4 serving utilities: 5.3 to 7.7¢/kWh, which qualifies but never replaces the state average.
Sublette, Wyoming shows no interconnection-queue project in the covered feeds, whether from real quiet or a feed not yet loaded. The federal EIA-860M inventory files no planned or under-construction generation in Sublette, Wyoming, a real zero rather than a gap. In eGRID, the balancing authority over Sublette shows 1,410.035 lb CO2 per MWh.
For Sublette, the USGS 2015 compilation records 658.15 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Sublette sits within commuting range of roughly 2,592 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Sublette here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Sublette, Wyoming settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Sublette, Wyoming requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Sublette, Wyoming are logged directly below, so each figure on this page can be traced back to its public dataset.