Price, WI: data center power outlook

Price, Wisconsin is served through the MISO market (Midcontinent Independent System Operator), and the figures below describe the public grid around a prospective data center site there. Price carries 13 mapped substations within its boundary, and the highest reachable grid access is 115 kV. Service in Price spans 6 utilities, with BAYFIELD ELECTRIC COOP, INC, JUMP RIVER ELECTRIC COOP INC, NORTH CENTRAL POWER CO INC among those mapped.

Grid position at a glance

Serving utilities
BAYFIELD ELECTRIC COOP, INC, JUMP RIVER ELECTRIC COOP INC, NORTH CENTRAL POWER CO INC, NORTHERN STATES POWER CO, PRICE ELECTRIC COOP INC, WPPI ENERGY
ISO / market
MISO (Midcontinent Independent System Operator)
Highest grid access
115 kV
Substations in county
13
Industrial retail rate
8.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
2 of 6 serving utilities: 8.5 to 9.6¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
982 lb CO2/MWh
Water withdrawals
20 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
11,769 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Price

The material below frames Price, Wisconsin for a prospective large load, drawing only on public sources. At 115 kV, Price sits in the transmission class that a large load would look to. The mapped layer places 13 substations across Price, a moderate density.

Interconnection over Price runs through the MISO market (Midcontinent Independent System Operator) and its rules. For Price, the rate shown is the state industrial average of 8.9 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Price that report an industrial rate span 2 of 6 serving utilities: 8.5 to 9.6¢/kWh, shown as context and never as the county rate.

Across the covered feeds, Price, Wisconsin carries no interconnection-queue project, from either real quiet or a feed not yet loaded. Price, Wisconsin has no EIA-860M generation on file, which reads as zero rather than as a gap. Price sits under a balancing authority that eGRID puts at 981.982 lb CO2 per MWh.

Price withdrew 20.14 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 11,769 people are employed in construction within a 120 km commute of Price (BLS QCEW), which frames staffing distance rather than free labour.

For Price, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Price, Wisconsin describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Price, Wisconsin, a specific address needs its own interconnection study, which this page does not attempt. The figures for Price, Wisconsin refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.