Polk, WI: data center power outlook
Polk, Wisconsin is served through the MISO market (Midcontinent Independent System Operator), and the figures below describe the public grid around a prospective data center site there. Polk carries 39 mapped substations within its boundary, and the highest reachable grid access is 161 kV. Service in Polk spans 9 utilities, with BARRON ELECTRIC COOP, DUNN COUNTY ELECTRIC COOP, EAST CENTRAL ENERGY among those mapped.
Grid position at a glance
- Serving utilities
- BARRON ELECTRIC COOP, DUNN COUNTY ELECTRIC COOP, EAST CENTRAL ENERGY, NORTHERN STATES POWER CO, NORTHERN STATES POWER CO - MINNESOTA, NORTHWESTERN WISCONSIN ELEC CO, POLK-BURNETT ELECTRIC COOP, ST CROIX ELECTRIC COOP, WPPI ENERGY
- ISO / market
- MISO (Midcontinent Independent System Operator)
- Highest grid access
- 161 kV
- Substations in county
- 39
- Industrial retail rate
- 8.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 5 of 9 serving utilities: 8.2 to 28.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 2 projects, 200 MW
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 9.2 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 89,365 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Polk
What follows is a screening-grade read of Polk, Wisconsin, built only from named public datasets. At 161 kV, Polk sits in the transmission class that a large load would look to. The mapped layer packs 39 substations into Polk, a dense spread of options.
Interconnection over Polk runs through the MISO market (Midcontinent Independent System Operator) and its rules. For Polk, the rate shown is the state industrial average of 8.9 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Polk that report an industrial rate span 5 of 9 serving utilities: 8.2 to 28.1¢/kWh, shown as context and never as the county rate.
The queue feeds show 2 projects for Polk, totalling 200 MW of requested capacity. Polk, Wisconsin has no EIA-860M generation on file, which reads as zero rather than as a gap. Polk sits under a balancing authority that eGRID puts at 981.982 lb CO2 per MWh.
Polk withdrew 9.15 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 89,365 people are employed in construction within a 120 km commute of Polk (BLS QCEW), which frames staffing distance rather than free labour.
For Polk, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Polk, Wisconsin describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Polk, Wisconsin, a specific address needs its own interconnection study, which this page does not attempt. The figures for Polk, Wisconsin refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.