Monroe, WI: data center power outlook
The grid around Monroe, Wisconsin is summarized here from public data, starting from the county's position in the MISO market (Midcontinent Independent System Operator). Inside Monroe the mapped layer shows 45 mapped substations, with grid access reaching 161 kV at its strongest point. Retail service across Monroe is split among 8 utilities, among them JACKSON ELECTRIC COOP, INC - (WI), NORTHERN STATES POWER CO, OAKDALE ELECTRIC COOP.
Grid position at a glance
- Serving utilities
- JACKSON ELECTRIC COOP, INC - (WI), NORTHERN STATES POWER CO, OAKDALE ELECTRIC COOP, SCENIC RIVERS ENERGY COOP, VERNON ELECTRIC COOP, VILLAGE OF CASHTON - (WI), WISCONSIN POWER & LIGHT CO, WPPI ENERGY
- ISO / market
- MISO (Midcontinent Independent System Operator)
- Highest grid access
- 161 kV
- Substations in county
- 45
- Industrial retail rate
- 8.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 4 of 8 serving utilities: 8.5 to 12.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 43 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 18,091 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Monroe
Read on for the public power picture of Monroe in Wisconsin, assembled for data center siting. Transmission-class access reaches 161 kV in Monroe at its strongest mapped point. Monroe contains 45 mapped substations, a dense footprint that spreads interconnection options across many points.
Wholesale activity over Monroe clears through the MISO market (Midcontinent Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Monroe carries the state industrial average retail rate of 8.9 cents per kWh from EIA-861, applied statewide. For Monroe, the per-utility spread is 4 of 8 serving utilities: 8.5 to 12.1¢/kWh, which qualifies but never replaces the state average.
For Monroe, Wisconsin, no queued project appears in the feeds currently covered. For Monroe, Wisconsin, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Monroe shows 981.982 lb CO2 per MWh.
For Monroe, the USGS 2015 compilation records 42.83 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Monroe sits within commuting range of roughly 18,091 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Monroe here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Monroe, Wisconsin settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Monroe, Wisconsin requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Monroe, Wisconsin are logged directly below, so each figure on this page can be traced back to its public dataset.