Langlade, WI: data center power outlook
The grid around Langlade, Wisconsin is summarized here from public data, starting from the county's position in the MISO market (Midcontinent Independent System Operator). Inside Langlade the mapped layer shows 7 mapped substations, with grid access reaching 115 kV at its strongest point. Retail service across Langlade is split among 5 utilities, among them BADGER POWER MARKETING AUTHORITY, NORTHERN STATES POWER CO, WISCONSIN POWER & LIGHT CO.
Grid position at a glance
- Serving utilities
- BADGER POWER MARKETING AUTHORITY, NORTHERN STATES POWER CO, WISCONSIN POWER & LIGHT CO, WISCONSIN PUBLIC SERVICE CORP, WPPI ENERGY
- ISO / market
- MISO (Midcontinent Independent System Operator)
- Highest grid access
- 115 kV
- Substations in county
- 7
- Industrial retail rate
- 8.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 5 serving utilities: 7.2 to 8.9¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 25 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 21,383 employed in construction within ~120 km (17 of 18 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Langlade
Read on for the public power picture of Langlade in Wisconsin, assembled for data center siting. Transmission-class access reaches 115 kV in Langlade at its strongest mapped point. Langlade contains 7 mapped substations, a moderate footprint spread across the service area.
Wholesale activity over Langlade clears through the MISO market (Midcontinent Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Langlade carries the state industrial average retail rate of 8.9 cents per kWh from EIA-861, applied statewide. For Langlade, the per-utility spread is 3 of 5 serving utilities: 7.2 to 8.9¢/kWh, which qualifies but never replaces the state average.
Langlade, Wisconsin shows no interconnection-queue project in the covered feeds, whether from real quiet or a feed not yet loaded. The federal EIA-860M inventory files no planned or under-construction generation in Langlade, Wisconsin, a real zero rather than a gap. In eGRID, the balancing authority over Langlade shows 981.982 lb CO2 per MWh.
For Langlade, the USGS 2015 compilation records 24.58 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Langlade sits within commuting range of roughly 21,383 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Langlade here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Langlade, Wisconsin settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Langlade, Wisconsin requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Langlade, Wisconsin are logged directly below, so each figure on this page can be traced back to its public dataset.