Mingo, WV: data center power outlook

The grid around Mingo, West Virginia is summarized here from public data, starting from the county's position in the PJM market (PJM Interconnection). Inside Mingo the mapped layer shows 17 mapped substations, with grid access reaching 138 kV at its strongest point. Retail service across Mingo is split among 3 utilities, among them APPALACHIAN POWER CO, BLACK DIAMOND POWER CO, KENTUCKY POWER CO.

Grid position at a glance

Serving utilities
APPALACHIAN POWER CO, BLACK DIAMOND POWER CO, KENTUCKY POWER CO
ISO / market
PJM (PJM Interconnection)
Highest grid access
138 kV
Substations in county
17
Industrial retail rate
8.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
1 of 3 serving utilities: 8.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
6.7 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
21,867 employed in construction within ~120 km (36 of 43 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Mingo

The sections below set out what public data shows about siting a large electrical load in Mingo, West Virginia. Transmission-class access reaches 138 kV in Mingo at its strongest mapped point. Mingo contains 17 mapped substations, a moderate footprint spread across the service area.

Wholesale activity over Mingo clears through the PJM market (PJM Interconnection), whose footprint sets how interconnection requests and capacity are handled. Mingo carries the state industrial average retail rate of 8.1 cents per kWh from EIA-861, applied statewide. For Mingo, the per-utility spread is 1 of 3 serving utilities: 8.8¢/kWh, which qualifies but never replaces the state average.

Mingo, West Virginia shows no interconnection-queue project in the covered feeds, whether from real quiet or a feed not yet loaded. The federal EIA-860M inventory files no planned or under-construction generation in Mingo, West Virginia, a real zero rather than a gap. In eGRID, the balancing authority over Mingo shows 716.09 lb CO2 per MWh.

For Mingo, the USGS 2015 compilation records 6.73 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Mingo sits within commuting range of roughly 21,867 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Mingo here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Mingo, West Virginia settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Mingo, West Virginia requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Mingo, West Virginia are logged directly below, so each figure on this page can be traced back to its public dataset.

Sources