Power by county
Warren, VA: data center power outlook
Warren, Virginia is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Warren carries 16 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in Warren spans 4 utilities, with RAPPAHANNOCK ELECTRIC COOP, SHENANDOAH VALLEY ELEC COOP, TOWN OF FRONT ROYAL among those mapped.
Grid position at a glance
- Serving utilities
- RAPPAHANNOCK ELECTRIC COOP, SHENANDOAH VALLEY ELEC COOP, TOWN OF FRONT ROYAL, VIRGINIA ELECTRIC & POWER CO
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 500 kV
- Substations in county
- 16
- Industrial retail rate
- 9.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 4 serving utilities: 6.0 to 9.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 12 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 194,863 employed in construction within ~120 km (47 of 51 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Warren
The material below frames Warren, Virginia for a prospective large load, drawing only on public sources. Grid access in Warren extends to 500 kV, a high-voltage line class. The mapped layer places 16 substations across Warren, a moderate density.
Interconnection over Warren runs through the PJM market (PJM Interconnection) and its rules. For Warren, the rate shown is the state industrial average of 9.4 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Warren that report an industrial rate span 3 of 4 serving utilities: 6.0 to 9.1¢/kWh, shown as context and never as the county rate.
No interconnection-queue project is on record for Warren, Virginia in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. Warren, Virginia has no EIA-860M generation on file, which reads as zero rather than as a gap. Warren sits under a balancing authority that eGRID puts at 716.09 lb CO2 per MWh.
Warren withdrew 11.79 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 194,863 people are employed in construction within a 120 km commute of Warren (BLS QCEW), which frames staffing distance rather than free labour.
For Warren, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Warren, Virginia describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Warren, Virginia, a specific address needs its own interconnection study, which this page does not attempt. The figures for Warren, Virginia refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.