Northampton, VA: data center power outlook
The grid around Northampton, Virginia is summarized here from public data, starting from the county's position in the PJM market (PJM Interconnection). Inside Northampton the mapped layer shows 9 mapped substations, with grid access reaching 69 kV at its strongest point. Retail electric service across Northampton comes from A & N ELECTRIC COOP.
Grid position at a glance
- Serving utilities
- A & N ELECTRIC COOP
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 69 kV
- Substations in county
- 9
- Industrial retail rate
- 9.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 1 serving utility: 9.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 3.2 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 45,841 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Northampton
Read on for the public power picture of Northampton in Virginia, assembled for data center siting. Grid access in Northampton peaks at 69 kV, below the transmission class most large loads look for. Northampton contains 9 mapped substations, a moderate footprint spread across the service area.
Wholesale activity over Northampton clears through the PJM market (PJM Interconnection), whose footprint sets how interconnection requests and capacity are handled. Northampton carries the state industrial average retail rate of 9.4 cents per kWh from EIA-861, applied statewide. For Northampton, the per-utility spread is 1 serving utility: 9.7¢/kWh, which qualifies but never replaces the state average.
Northampton, Virginia shows no interconnection-queue project in the covered feeds, whether from real quiet or a feed not yet loaded. For Northampton, Virginia, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Northampton shows 716.09 lb CO2 per MWh.
For Northampton, the USGS 2015 compilation records 3.23 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Northampton sits within commuting range of roughly 45,841 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Northampton here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Northampton, Virginia settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Northampton, Virginia requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Northampton, Virginia are logged directly below, so each figure on this page can be traced back to its public dataset.