Manassas, VA: data center power outlook
The grid around Manassas, Virginia is summarized here from public data, starting from the county's position in the PJM market (PJM Interconnection). Inside Manassas the mapped layer shows 12 mapped substations, with grid access reaching 230 kV at its strongest point. Retail service across Manassas is split among 3 utilities, among them CITY OF MANASSAS - (VA), NORTHERN VIRGINIA ELEC COOP, VIRGINIA ELECTRIC & POWER CO.
Grid position at a glance
- Serving utilities
- CITY OF MANASSAS - (VA), NORTHERN VIRGINIA ELEC COOP, VIRGINIA ELECTRIC & POWER CO
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 230 kV
- Substations in county
- 12
- Industrial retail rate
- 9.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 serving utilities: 6.0 to 7.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 0.5 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 257,388 employed in construction within ~120 km (50 of 52 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Manassas
Read on for the public power picture of Manassas in Virginia, assembled for data center siting. Transmission-class access reaches 230 kV in Manassas at its strongest mapped point. Manassas contains 12 mapped substations, a moderate footprint spread across the service area.
Wholesale activity over Manassas clears through the PJM market (PJM Interconnection), whose footprint sets how interconnection requests and capacity are handled. Manassas carries the state industrial average retail rate of 9.4 cents per kWh from EIA-861, applied statewide. For Manassas, the per-utility spread is 3 serving utilities: 6.0 to 7.4¢/kWh, which qualifies but never replaces the state average.
Manassas, Virginia has nothing in the interconnection queue across the feeds covered here, quiet or uningested. No generation is filed as planned or under construction in Manassas, Virginia in the federal EIA-860M inventory, a measured zero rather than missing data. In eGRID, the balancing authority over Manassas shows 716.09 lb CO2 per MWh.
For Manassas, the USGS 2015 compilation records 0.51 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Manassas sits within commuting range of roughly 257,388 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Manassas here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Manassas, Virginia settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Manassas, Virginia requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Manassas, Virginia are logged directly below, so each figure on this page can be traced back to its public dataset.