Power by county

Davis, UT: data center power outlook

For Davis, Utah, the public grid picture begins with its place in an area outside an organized wholesale market and the infrastructure mapped inside the county. Grid access across Davis tops out at 345 kV, over a footprint of 78 mapped substations. In Davis, 5 utilities share the retail territory, among them CITY OF BOUNTIFUL, KAYSVILLE CITY CORPORATION, MORGAN CITY - (UT).

Grid position at a glance

Serving utilities
CITY OF BOUNTIFUL, KAYSVILLE CITY CORPORATION, MORGAN CITY - (UT), PACIFICORP, WAPA-- WESTERN AREA POWER ADMINISTRATION
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
345 kV
Substations in county
78
Industrial retail rate
8.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 5 serving utilities: 3.1 to 8.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
1,410 lb CO2/MWh
Water withdrawals
72 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
122,402 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Davis

This page gathers the public grid evidence for Davis, Utah that bears on a large new load. The highest mapped voltage in Davis is 345 kV, in the high-voltage transmission class. Davis carries 78 substations, a dense footprint across the county.

Davis, Utah lies outside an organized wholesale market, so generation and transmission are arranged bilaterally and through the local utility rather than a central market operator. The state industrial average retail rate is 8.4 cents per kWh, drawn from EIA-861 and applied to Davis at the state level rather than as a county rate. The serving utilities in Davis that publish a rate range 3 of 5 serving utilities: 3.1 to 8.1¢/kWh, a spread kept separate from the state average.

Davis, Utah has nothing in the interconnection queue across the feeds covered here, quiet or uningested. No generation is filed as planned or under construction in Davis, Utah in the federal EIA-860M inventory, a measured zero rather than missing data. Grid carbon intensity for Davis, via its balancing authority, is 1,410.035 lb CO2 per MWh in eGRID.

USGS 2015 puts freshwater withdrawals across Davis at 71.94 million gallons per day for all uses, a measure of use, not spare supply. Within roughly a 120 km commute of Davis, about 122,402 people are employed in construction (BLS QCEW), which speaks to how far crews for a multi-year build would travel, not to labour known to be free.

Read the Davis figures as screening-grade context: they describe the surrounding grid, not a specific parcel. The numbers for Davis, Utah qualify one another, so grid access, substation density, market membership, and rate are meant to be read as a set, not in isolation. Past this screening view, siting in Davis, Utah turns on a study of a particular address, something no county-level page can stand in for. Every number shown for Davis, Utah traces to a public source listed below, with its retrieval date, so the provenance is auditable rather than asserted.