Power by county

Midland, TX: data center power outlook

Midland, Texas is served through the SPP market (Southwest Power Pool), and the figures below describe the public grid around a prospective data center site there. Midland carries 34 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Midland spans 5 utilities, with AEP TEXAS NORTH COMPANY, CONCHO VALLEY ELEC COOP INC, ONCOR ELECTRIC DELIVERY COMPANY LLC among those mapped.

Grid position at a glance

Serving utilities
AEP TEXAS NORTH COMPANY, CONCHO VALLEY ELEC COOP INC, ONCOR ELECTRIC DELIVERY COMPANY LLC, SOUTHWEST TEXAS ELEC COOP, INC, SOUTHWESTERN PUBLIC SERVICE CO
ISO / market
SPP (Southwest Power Pool)
Highest grid access
345 kV
Substations in county
34
Industrial retail rate
6.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 5 serving utilities: 4.9 to 7.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
6 projects, 854 MW
Proposed generation
22 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
734 lb CO2/MWh
Water withdrawals
9.2 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
21,921 employed in construction within ~120 km (10 of 17 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Midland

The material below frames Midland, Texas for a prospective large load, drawing only on public sources. Grid access in Midland extends to 345 kV, a high-voltage line class. The mapped layer packs 34 substations into Midland, a dense spread of options.

Interconnection over Midland runs through the SPP market (Southwest Power Pool) and its rules. For Midland, the rate shown is the state industrial average of 6.5 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Midland that report an industrial rate span 3 of 5 serving utilities: 4.9 to 7.7¢/kWh, shown as context and never as the county rate.

The queue feeds show 6 projects for Midland, totalling 853.84 MW of requested capacity. EIA-860M records 22.2 MW planned or under construction for Midland. Midland sits under a balancing authority that eGRID puts at 734.003 lb CO2 per MWh.

Midland withdrew 9.17 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 21,921 people are employed in construction within a 120 km commute of Midland (BLS QCEW), which frames staffing distance rather than free labour.

For Midland, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Midland, Texas describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Midland, Texas, a specific address needs its own interconnection study, which this page does not attempt. The figures for Midland, Texas refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources