Power by county

Martin, TX: data center power outlook

The grid around Martin, Texas is summarized here from public data, starting from the county's position in the SPP market (Southwest Power Pool). Inside Martin the mapped layer shows 9 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Martin is split among 5 utilities, among them CONCHO VALLEY ELEC COOP INC, LEA COUNTY ELECTRIC COOP, INC, LYNTEGAR ELECTRIC COOP, INC.

Grid position at a glance

Serving utilities
CONCHO VALLEY ELEC COOP INC, LEA COUNTY ELECTRIC COOP, INC, LYNTEGAR ELECTRIC COOP, INC, ONCOR ELECTRIC DELIVERY COMPANY LLC, SOUTHWESTERN PUBLIC SERVICE CO
ISO / market
SPP (Southwest Power Pool)
Highest grid access
345 kV
Substations in county
9
Industrial retail rate
6.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 of 5 serving utilities: 4.9 to 8.9¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
3 projects, 492 MW
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
734 lb CO2/MWh
Water withdrawals
37 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
21,020 employed in construction within ~120 km (11 of 19 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Martin

The sections below set out what public data shows about siting a large electrical load in Martin, Texas. At 345 kV, Martin carries high-voltage transmission at its strongest mapped point. Martin contains 9 mapped substations, a moderate footprint spread across the service area.

Wholesale activity over Martin clears through the SPP market (Southwest Power Pool), whose footprint sets how interconnection requests and capacity are handled. Martin carries the state industrial average retail rate of 6.5 cents per kWh from EIA-861, applied statewide. For Martin, the per-utility spread is 4 of 5 serving utilities: 4.9 to 8.9¢/kWh, which qualifies but never replaces the state average.

Martin carries 3 projects in the interconnection queue, totalling 491.93 MW of requested capacity. The federal EIA-860M inventory files no planned or under-construction generation in Martin, Texas, a real zero rather than a gap. In eGRID, the balancing authority over Martin shows 734.003 lb CO2 per MWh.

For Martin, the USGS 2015 compilation records 37.42 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Martin sits within commuting range of roughly 21,020 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Martin here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Martin, Texas settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Martin, Texas requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Martin, Texas are logged directly below, so each figure on this page can be traced back to its public dataset.