Power by county
Blanco, TX: data center power outlook
Blanco, Texas is served through the ERCOT market (Electric Reliability Council of Texas), and the figures below describe the public grid around a prospective data center site there. Blanco carries 7 mapped substations within its boundary, and the highest reachable grid access is 138 kV. Service in Blanco spans 7 utilities, with AEP TEXAS NORTH COMPANY, BANDERA ELECTRIC COOP, INC, BLUEBONNET ELECTRIC COOP, INC among those mapped.
Grid position at a glance
- Serving utilities
- AEP TEXAS NORTH COMPANY, BANDERA ELECTRIC COOP, INC, BLUEBONNET ELECTRIC COOP, INC, CENTRAL TEXAS ELEC COOP, INC, GUADALUPE VALLEY ELEC COOP INC, HAMILTON COUNTY ELEC COOP ASSN, PEDERNALES ELECTRIC COOP, INC
- ISO / market
- ERCOT (Electric Reliability Council of Texas)
- Highest grid access
- 138 kV
- Substations in county
- 7
- Industrial retail rate
- 6.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 5 of 7 serving utilities: 5.4 to 10.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 1 projects, 154 MW
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 734 lb CO2/MWh
- Water withdrawals
- 2.8 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 156,892 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Blanco
What follows is a screening-grade read of Blanco, Texas, built only from named public datasets. At 138 kV, Blanco sits in the transmission class that a large load would look to. The mapped layer places 7 substations across Blanco, a moderate density.
Interconnection over Blanco runs through the ERCOT market (Electric Reliability Council of Texas) and its rules. For Blanco, the rate shown is the state industrial average of 6.5 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Blanco that report an industrial rate span 5 of 7 serving utilities: 5.4 to 10.2¢/kWh, shown as context and never as the county rate.
The queue feeds show 1 project for Blanco, totalling 153.62 MW of requested capacity. Blanco, Texas has no EIA-860M generation on file, which reads as zero rather than as a gap. Blanco sits under a balancing authority that eGRID puts at 734.003 lb CO2 per MWh.
Blanco withdrew 2.81 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 156,892 people are employed in construction within a 120 km commute of Blanco (BLS QCEW), which frames staffing distance rather than free labour.
For Blanco, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Blanco, Texas describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Blanco, Texas, a specific address needs its own interconnection study, which this page does not attempt. The figures for Blanco, Texas refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.