Anderson, TN: data center power outlook

Anderson, Tennessee is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Anderson carries 55 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in Anderson spans 6 utilities, with CITY OF CLINTON - (TN), CITY OF LAFOLLETTE, CITY OF LENOIR - (TN) among those mapped.

Grid position at a glance

Serving utilities
CITY OF CLINTON - (TN), CITY OF LAFOLLETTE, CITY OF LENOIR - (TN), CITY OF OAK RIDGE, KNOXVILLE UTILITIES BOARD, PLATEAU ELECTRIC COOPERATIVE
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
500 kV
Substations in county
55
Industrial retail rate
6.7¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
6 serving utilities: 5.1 to 10.0¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
641 lb CO2/MWh
Water withdrawals
204 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
36,423 employed in construction within ~120 km (36 of 42 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Anderson

The material below frames Anderson, Tennessee for a prospective large load, drawing only on public sources. Grid access in Anderson extends to 500 kV, a high-voltage line class. The mapped layer packs 55 substations into Anderson, a dense spread of options.

Sitting outside any organized market, Anderson, Tennessee handles interconnection through its utility rather than a central operator. For Anderson, the rate shown is the state industrial average of 6.7 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Anderson that report an industrial rate span 6 serving utilities: 5.1 to 10.0¢/kWh, shown as context and never as the county rate.

The covered queue feeds list nothing for Anderson, Tennessee, which may be quiet or simply uningested. Anderson, Tennessee has no EIA-860M generation on file, which reads as zero rather than as a gap. Anderson sits under a balancing authority that eGRID puts at 641.018 lb CO2 per MWh.

Anderson withdrew 203.73 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 36,423 people are employed in construction within a 120 km commute of Anderson (BLS QCEW), which frames staffing distance rather than free labour.

For Anderson, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Anderson, Tennessee describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Anderson, Tennessee, a specific address needs its own interconnection study, which this page does not attempt. The figures for Anderson, Tennessee refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.