Power by county

Lee, SC: data center power outlook

Lee, South Carolina is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Lee carries 9 mapped substations within its boundary, and the highest reachable grid access is 230 kV. Service in Lee spans 4 utilities, with BLACK RIVER ELECTRIC COOP, INC - (SC), DUKE ENERGY CAROLINAS, LLC, DUKE ENERGY PROGRESS - (NC) among those mapped.

Grid position at a glance

Serving utilities
BLACK RIVER ELECTRIC COOP, INC - (SC), DUKE ENERGY CAROLINAS, LLC, DUKE ENERGY PROGRESS - (NC), PEE DEE ELECTRIC COOP, INC
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
230 kV
Substations in county
9
Industrial retail rate
7.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 4 serving utilities: 7.0 to 8.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
60 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
482 lb CO2/MWh
Water withdrawals
6.8 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
44,403 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Lee

What follows is a screening-grade read of Lee, South Carolina, built only from named public datasets. At 230 kV, Lee sits in the transmission class that a large load would look to. The mapped layer places 9 substations across Lee, a moderate density.

Because Lee, South Carolina sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For Lee, the rate shown is the state industrial average of 7.1 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Lee that report an industrial rate span 3 of 4 serving utilities: 7.0 to 8.1¢/kWh, shown as context and never as the county rate.

Across the covered feeds, Lee, South Carolina carries no interconnection-queue project, from either real quiet or a feed not yet loaded. EIA-860M records 60 MW planned or under construction for Lee. Lee sits under a balancing authority that eGRID puts at 481.506 lb CO2 per MWh.

Lee withdrew 6.75 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 44,403 people are employed in construction within a 120 km commute of Lee (BLS QCEW), which frames staffing distance rather than free labour.

For Lee, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Lee, South Carolina describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Lee, South Carolina, a specific address needs its own interconnection study, which this page does not attempt. The figures for Lee, South Carolina refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.