Power by county
Anderson, SC: data center power outlook
Anderson, South Carolina is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Anderson carries 114 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in Anderson spans 7 utilities, with BLUE RIDGE ELECTRIC COOP INC - (SC), DUKE ENERGY CAROLINAS, LLC, EASLEY COMBINED UTILITY SYSTEM among those mapped.
Grid position at a glance
- Serving utilities
- BLUE RIDGE ELECTRIC COOP INC - (SC), DUKE ENERGY CAROLINAS, LLC, EASLEY COMBINED UTILITY SYSTEM, GEORGIA POWER CO, HART ELECTRIC MEMBER CORP, LAURENS ELECTRIC COOP, INC, LITTLE RIVER ELECTRIC COOP INC
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 500 kV
- Substations in county
- 114
- Industrial retail rate
- 7.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 4 of 7 serving utilities: 7.0 to 9.0¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 485 lb CO2/MWh
- Water withdrawals
- 59 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 64,381 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Anderson
The material below frames Anderson, South Carolina for a prospective large load, drawing only on public sources. Grid access in Anderson extends to 500 kV, a high-voltage line class. The mapped layer packs 114 substations into Anderson, a dense spread of options.
Sitting outside any organized market, Anderson, South Carolina handles interconnection through its utility rather than a central operator. For Anderson, the rate shown is the state industrial average of 7.1 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Anderson that report an industrial rate span 4 of 7 serving utilities: 7.0 to 9.0¢/kWh, shown as context and never as the county rate.
Across the covered feeds, Anderson, South Carolina carries no interconnection-queue project, from either real quiet or a feed not yet loaded. EIA-860M lists nothing planned or under construction for Anderson, South Carolina, which is a national filing and so a real zero. Anderson sits under a balancing authority that eGRID puts at 484.617 lb CO2 per MWh.
Anderson withdrew 59.41 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 64,381 people are employed in construction within a 120 km commute of Anderson (BLS QCEW), which frames staffing distance rather than free labour.
For Anderson, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Anderson, South Carolina describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Anderson, South Carolina, a specific address needs its own interconnection study, which this page does not attempt. The figures for Anderson, South Carolina refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.