Snyder sits in the PJM market (PJM Interconnection); what follows is the screening-grade grid picture for Snyder, Pennsylvania, drawn from public datasets. Counting from the mapped infrastructure, Snyder holds 8 mapped substations and reaches 500 kV. Snyder is covered by 2 retail service territories, including PENNSYLVANIA ELECTRIC CO, PPL ELECTRIC UTILITIES CORP.
Grid position at a glance
- Serving utilities
- PENNSYLVANIA ELECTRIC CO, PPL ELECTRIC UTILITIES CORP
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 500 kV
- Substations in county
- 8
- Industrial retail rate
- 9.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- No per-utility rate on fileLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- 18 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 5.1 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 81,317 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Snyder
Below, Snyder in Pennsylvania is described from public data as a starting point for siting diligence. Snyder reaches 500 kV, a high-voltage transmission class, at its strongest mapped point of grid access. With 8 substations mapped, Snyder has a moderate spread of interconnection points.
Snyder falls inside the PJM market (PJM Interconnection), which governs how its interconnection requests and capacity move. The rate for Snyder is the 9.4 cents per kWh state industrial average (EIA-861), the same figure the map colours by.
The covered queue feeds list nothing for Snyder, Pennsylvania, which may be quiet or simply uningested. Snyder has 18 MW of planned or under-construction generation on file in EIA-860M. The balancing authority covering Snyder carries a grid carbon intensity of 716.09 lb CO2 per MWh in eGRID.
Reported freshwater withdrawals for all uses in Snyder are 5.12 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Snyder, some 81,317 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.
These numbers for Snyder are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Snyder, Pennsylvania together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Snyder, Pennsylvania is an address-level interconnection study; the county figures here only narrow where to look. For Snyder, Pennsylvania, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.