Power by county
Schuylkill, PA: data center power outlook
Schuylkill, Pennsylvania is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Schuylkill carries 49 mapped substations within its boundary, and the highest reachable grid access is 230 kV. Service in Schuylkill spans 4 utilities, with BOROUGH OF SCHUYLKILL HAVEN - (PA), BOROUGH OF ST CLAIR - (PA), METROPOLITAN EDISON CO among those mapped.
Grid position at a glance
- Serving utilities
- BOROUGH OF SCHUYLKILL HAVEN - (PA), BOROUGH OF ST CLAIR - (PA), METROPOLITAN EDISON CO, PPL ELECTRIC UTILITIES CORP
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 230 kV
- Substations in county
- 49
- Industrial retail rate
- 9.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- No per-utility rate on fileLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 33 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 171,861 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Schuylkill
The material below frames Schuylkill, Pennsylvania for a prospective large load, drawing only on public sources. At 230 kV, Schuylkill sits in the transmission class that a large load would look to. The mapped layer packs 49 substations into Schuylkill, a dense spread of options.
Interconnection over Schuylkill runs through the PJM market (PJM Interconnection) and its rules. For Schuylkill, the rate shown is the state industrial average of 9.4 cents per kWh (EIA-861), a state figure and not a county-specific one.
No interconnection-queue project is on record for Schuylkill, Pennsylvania in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. Nothing is on file for Schuylkill, Pennsylvania in EIA-860M as planned or under construction, which counts as a measured zero. Schuylkill sits under a balancing authority that eGRID puts at 716.09 lb CO2 per MWh.
Schuylkill withdrew 32.86 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 171,861 people are employed in construction within a 120 km commute of Schuylkill (BLS QCEW), which frames staffing distance rather than free labour.
For Schuylkill, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Schuylkill, Pennsylvania describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Schuylkill, Pennsylvania, a specific address needs its own interconnection study, which this page does not attempt. The figures for Schuylkill, Pennsylvania refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.