Linn, OR: data center power outlook

Linn, Oregon is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Linn carries 50 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in Linn spans 7 utilities, with BONNEVILLE POWER ADMINISTRATION, CENTRAL ELECTRIC COOP INC - (OR), CITY OF EUGENE - (OR) among those mapped.

Grid position at a glance

Serving utilities
BONNEVILLE POWER ADMINISTRATION, CENTRAL ELECTRIC COOP INC - (OR), CITY OF EUGENE - (OR), CONSUMERS POWER, INC, EMERALD PEOPLE'S UTILITY DIST, LANE ELECTRIC COOP INC, PACIFICORP
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
500 kV
Substations in county
50
Industrial retail rate
8.3¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
6 of 7 serving utilities: 2.0 to 9.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
212 lb CO2/MWh
Water withdrawals
152 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
51,972 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Linn

What follows is a screening-grade read of Linn, Oregon, built only from named public datasets. Grid access in Linn extends to 500 kV, a high-voltage line class. The mapped layer packs 50 substations into Linn, a dense spread of options.

Sitting outside any organized market, Linn, Oregon handles interconnection through its utility rather than a central operator. For Linn, the rate shown is the state industrial average of 8.3 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Linn that report an industrial rate span 6 of 7 serving utilities: 2.0 to 9.7¢/kWh, shown as context and never as the county rate.

No interconnection-queue project is on record for Linn, Oregon in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. Linn, Oregon has no EIA-860M generation on file, which reads as zero rather than as a gap. Linn sits under a balancing authority that eGRID puts at 212.458 lb CO2 per MWh.

Linn withdrew 151.5 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 51,972 people are employed in construction within a 120 km commute of Linn (BLS QCEW), which frames staffing distance rather than free labour.

For Linn, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Linn, Oregon describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Linn, Oregon, a specific address needs its own interconnection study, which this page does not attempt. The figures for Linn, Oregon refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources