Klamath, OR: data center power outlook

The grid around Klamath, Oregon is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Klamath the mapped layer shows 50 mapped substations, with grid access reaching 500 kV at its strongest point. Retail service across Klamath is split among 7 utilities, among them BONNEVILLE POWER ADMINISTRATION, LANE ELECTRIC COOP INC, MIDSTATE ELECTRIC COOP, INC.

Grid position at a glance

Serving utilities
BONNEVILLE POWER ADMINISTRATION, LANE ELECTRIC COOP INC, MIDSTATE ELECTRIC COOP, INC, PACIFICORP, SURPRISE VALLEY ELECTRIFICATION, UMPQUA INDIAN UTILITY COOPERATIVE, WAPA-- WESTERN AREA POWER ADMINISTRATION
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
500 kV
Substations in county
50
Industrial retail rate
8.3¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 of 7 serving utilities: 7.4 to 11.9¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
2 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
212 lb CO2/MWh
Water withdrawals
683 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
8,675 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Klamath

Read on for the public power picture of Klamath in Oregon, assembled for data center siting. At 500 kV, Klamath carries high-voltage transmission at its strongest mapped point. Klamath contains 50 mapped substations, a dense footprint that spreads interconnection options across many points.

No organized wholesale market covers Klamath, Oregon, so capacity moves through the local utility and bilateral agreements. Klamath carries the state industrial average retail rate of 8.3 cents per kWh from EIA-861, applied statewide. For Klamath, the per-utility spread is 4 of 7 serving utilities: 7.4 to 11.9¢/kWh, which qualifies but never replaces the state average.

For Klamath, Oregon, no queued project appears in the feeds currently covered. In Klamath, 2 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Klamath shows 212.458 lb CO2 per MWh.

For Klamath, the USGS 2015 compilation records 683.45 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Klamath sits within commuting range of roughly 8,675 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Klamath here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Klamath, Oregon settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Klamath, Oregon requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Klamath, Oregon are logged directly below, so each figure on this page can be traced back to its public dataset.