Power by county
Haskell, OK: data center power outlook
The grid around Haskell, Oklahoma is summarized here from public data, starting from the county's position in the SPP market (Southwest Power Pool). Inside Haskell the mapped layer shows 10 mapped substations, with grid access reaching 161 kV at its strongest point. Retail service across Haskell is split among 4 utilities, among them COOKSON HILLS ELEC COOP, INC, KIAMICHI ELECTRIC COOP, INC, OKLAHOMA GAS & ELECTRIC CO.
Grid position at a glance
- Serving utilities
- COOKSON HILLS ELEC COOP, INC, KIAMICHI ELECTRIC COOP, INC, OKLAHOMA GAS & ELECTRIC CO, PUBLIC SERVICE CO OF OKLAHOMA
- ISO / market
- SPP (Southwest Power Pool)
- Highest grid access
- 161 kV
- Substations in county
- 10
- Industrial retail rate
- 6.2¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 4 serving utilities: 5.5 to 10.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 872 lb CO2/MWh
- Water withdrawals
- 2.7 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 18,947 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Haskell
Read on for the public power picture of Haskell in Oklahoma, assembled for data center siting. Transmission-class access reaches 161 kV in Haskell at its strongest mapped point. Haskell contains 10 mapped substations, a moderate footprint spread across the service area.
Wholesale activity over Haskell clears through the SPP market (Southwest Power Pool), whose footprint sets how interconnection requests and capacity are handled. Haskell carries the state industrial average retail rate of 6.2 cents per kWh from EIA-861, applied statewide. For Haskell, the per-utility spread is 4 serving utilities: 5.5 to 10.1¢/kWh, which qualifies but never replaces the state average.
Haskell, Oklahoma shows no interconnection-queue project in the covered feeds, whether from real quiet or a feed not yet loaded. No generation is filed as planned or under construction in Haskell, Oklahoma in the federal EIA-860M inventory, a measured zero rather than missing data. In eGRID, the balancing authority over Haskell shows 871.526 lb CO2 per MWh.
For Haskell, the USGS 2015 compilation records 2.72 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Haskell sits within commuting range of roughly 18,947 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Haskell here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Haskell, Oklahoma settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Haskell, Oklahoma requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Haskell, Oklahoma are logged directly below, so each figure on this page can be traced back to its public dataset.