The grid around Beaver, Oklahoma is summarized here from public data, starting from the county's position in the SPP market (Southwest Power Pool). Inside Beaver the mapped layer shows 23 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Beaver is split among 7 utilities, among them CMS ELECTRIC COOP INC, NORTH PLAINS ELECTRIC COOP INC, NORTHWESTERN ELECTRIC COOP INC - (OK).
Grid position at a glance
- Serving utilities
- CMS ELECTRIC COOP INC, NORTH PLAINS ELECTRIC COOP INC, NORTHWESTERN ELECTRIC COOP INC - (OK), PIONEER ELECTRIC COOP, INC - (KS), SOUTHERN PIONEER ELECTRIC COMPANY, SOUTHWESTERN PUBLIC SERVICE CO, TRI-COUNTY ELECTRIC COOP, INC (OK)
- ISO / market
- SPP (Southwest Power Pool)
- Highest grid access
- 345 kV
- Substations in county
- 23
- Industrial retail rate
- 6.2¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 7 serving utilities: 6.8 to 9.0¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 872 lb CO2/MWh
- Water withdrawals
- 58 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 2,419 employed in construction within ~120 km (12 of 19 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Beaver
Read on for the public power picture of Beaver in Oklahoma, assembled for data center siting. At 345 kV, Beaver carries high-voltage transmission at its strongest mapped point. Beaver contains 23 mapped substations, a dense footprint that spreads interconnection options across many points.
Wholesale activity over Beaver clears through the SPP market (Southwest Power Pool), whose footprint sets how interconnection requests and capacity are handled. Beaver carries the state industrial average retail rate of 6.2 cents per kWh from EIA-861, applied statewide. For Beaver, the per-utility spread is 2 of 7 serving utilities: 6.8 to 9.0¢/kWh, which qualifies but never replaces the state average.
For Beaver, Oklahoma, no queued project appears in the feeds currently covered. No generation is filed as planned or under construction in Beaver, Oklahoma in the federal EIA-860M inventory, a measured zero rather than missing data. In eGRID, the balancing authority over Beaver shows 871.526 lb CO2 per MWh.
For Beaver, the USGS 2015 compilation records 58.4 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Beaver sits within commuting range of roughly 2,419 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Beaver here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Beaver, Oklahoma settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Beaver, Oklahoma requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Beaver, Oklahoma are logged directly below, so each figure on this page can be traced back to its public dataset.