Seneca, OH: data center power outlook
Seneca sits in the PJM market (PJM Interconnection); what follows is the screening-grade grid picture for Seneca, Ohio, drawn from public datasets. Counting from the mapped infrastructure, Seneca holds 22 mapped substations and reaches 345 kV. Seneca is covered by 7 retail service territories, including FIRELANDS ELECTRIC COOP, INC, HANCOCK-WOOD ELECTRIC COOP INC, NORTH CENTRAL ELEC COOP, INC.
Grid position at a glance
- Serving utilities
- FIRELANDS ELECTRIC COOP, INC, HANCOCK-WOOD ELECTRIC COOP INC, NORTH CENTRAL ELEC COOP, INC, OHIO EDISON CO, OHIO POWER CO, THE TOLEDO EDISON CO, VILLAGE OF REPUBLIC - (OH)
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 345 kV
- Substations in county
- 22
- Industrial retail rate
- 8.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 4 of 7 serving utilities: 1.8 to 11.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 7.0 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 58,342 employed in construction within ~120 km (31 of 32 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Seneca
Below, Seneca in Ohio is described from public data as a starting point for siting diligence. Seneca reaches 345 kV, a high-voltage transmission class, at its strongest mapped point of grid access. With 22 substations mapped, Seneca offers interconnection points across many locations.
Seneca falls inside the PJM market (PJM Interconnection), which governs how its interconnection requests and capacity move. The rate for Seneca is the 8.5 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Seneca, reported per-utility industrial rates cover 4 of 7 serving utilities: 1.8 to 11.1¢/kWh, offered only as context beneath the state figure.
The covered queue feeds list nothing for Seneca, Ohio, which may be quiet or simply uningested. Seneca, Ohio has no EIA-860M generation on file, which reads as zero rather than as a gap. The balancing authority covering Seneca carries a grid carbon intensity of 716.09 lb CO2 per MWh in eGRID.
Reported freshwater withdrawals for all uses in Seneca are 6.96 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Seneca, some 58,342 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.
These numbers for Seneca are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Seneca, Ohio together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Seneca, Ohio is an address-level interconnection study; the county figures here only narrow where to look. For Seneca, Ohio, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.