Geauga, OH: data center power outlook

Geauga sits in the PJM market (PJM Interconnection); what follows is the screening-grade grid picture for Geauga, Ohio, drawn from public datasets. Counting from the mapped infrastructure, Geauga holds 13 mapped substations and reaches 345 kV. Geauga is covered by 3 retail service territories, including CITY OF CLEVELAND - (OH), CLEVELAND ELECTRIC ILLUM CO, OHIO EDISON CO.

Grid position at a glance

Serving utilities
CITY OF CLEVELAND - (OH), CLEVELAND ELECTRIC ILLUM CO, OHIO EDISON CO
ISO / market
PJM (PJM Interconnection)
Highest grid access
345 kV
Substations in county
13
Industrial retail rate
8.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 serving utilities: 1.8 to 9.3¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
8.7 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
87,422 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Geauga

Everything here about Geauga, Ohio comes from public federal and state records, with the gaps left visible. Geauga reaches 345 kV, a high-voltage transmission class, at its strongest mapped point of grid access. With 13 substations mapped, Geauga has a moderate spread of interconnection points.

Geauga falls inside the PJM market (PJM Interconnection), which governs how its interconnection requests and capacity move. The rate for Geauga is the 8.5 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Geauga, reported per-utility industrial rates cover 3 serving utilities: 1.8 to 9.3¢/kWh, offered only as context beneath the state figure.

The covered queue feeds list nothing for Geauga, Ohio, which may be quiet or simply uningested. Geauga, Ohio has no EIA-860M generation on file, which reads as zero rather than as a gap. The balancing authority covering Geauga carries a grid carbon intensity of 716.09 lb CO2 per MWh in eGRID.

Reported freshwater withdrawals for all uses in Geauga are 8.72 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Geauga, some 87,422 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.

These numbers for Geauga are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Geauga, Ohio together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Geauga, Ohio is an address-level interconnection study; the county figures here only narrow where to look. For Geauga, Ohio, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.