Power by county

Coshocton, OH: data center power outlook

Coshocton, Ohio is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Coshocton carries 13 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Coshocton spans 5 utilities, with FRONTIER POWER COMPANY, GUERNSEY-MUSKINGUM EL COOP INC, HOLMES-WAYNE ELECTRIC COOP INC among those mapped.

Grid position at a glance

Serving utilities
FRONTIER POWER COMPANY, GUERNSEY-MUSKINGUM EL COOP INC, HOLMES-WAYNE ELECTRIC COOP INC, LICKING RURAL ELECTRIC INC, OHIO POWER CO
ISO / market
PJM (PJM Interconnection)
Highest grid access
345 kV
Substations in county
13
Industrial retail rate
8.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 of 5 serving utilities: 2.6 to 14.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
39 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
110,870 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Coshocton

What follows is a screening-grade read of Coshocton, Ohio, built only from named public datasets. Grid access in Coshocton extends to 345 kV, a high-voltage line class. The mapped layer places 13 substations across Coshocton, a moderate density.

Interconnection over Coshocton runs through the PJM market (PJM Interconnection) and its rules. For Coshocton, the rate shown is the state industrial average of 8.5 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Coshocton that report an industrial rate span 4 of 5 serving utilities: 2.6 to 14.2¢/kWh, shown as context and never as the county rate.

The covered queue feeds list nothing for Coshocton, Ohio, which may be quiet or simply uningested. Nothing is on file for Coshocton, Ohio in EIA-860M as planned or under construction, which counts as a measured zero. Coshocton sits under a balancing authority that eGRID puts at 716.09 lb CO2 per MWh.

Coshocton withdrew 38.95 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 110,870 people are employed in construction within a 120 km commute of Coshocton (BLS QCEW), which frames staffing distance rather than free labour.

For Coshocton, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Coshocton, Ohio describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Coshocton, Ohio, a specific address needs its own interconnection study, which this page does not attempt. The figures for Coshocton, Ohio refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources