Power by county

Nassau, NY: data center power outlook

The grid around Nassau, New York is summarized here from public data, starting from the county's position in the NYISO market (New York Independent System Operator). Inside Nassau the mapped layer shows 93 mapped substations, with grid access reaching 500 kV at its strongest point. Retail service across Nassau is split among 6 utilities, among them CONSOLIDATED EDISON CO-NY INC, FISHERS ISLAND UTILITY CO INC, LONG ISLAND POWER AUTHORITY.

Grid position at a glance

Serving utilities
CONSOLIDATED EDISON CO-NY INC, FISHERS ISLAND UTILITY CO INC, LONG ISLAND POWER AUTHORITY, NORTH SHORE TOWERS APTS INC, VILLAGE OF FREEPORT - (NY), VILLAGE OF ROCKVILLE CENTRE - (NY)
ISO / market
NYISO (New York Independent System Operator)
Highest grid access
500 kV
Substations in county
93
Industrial retail rate
9.6¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
1 of 6 serving utilities: 26.0¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
3 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
479 lb CO2/MWh
Water withdrawals
205 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
439,041 employed in construction within ~120 km (31 of 32 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Nassau

The sections below set out what public data shows about siting a large electrical load in Nassau, New York. At 500 kV, Nassau carries high-voltage transmission at its strongest mapped point. Nassau contains 93 mapped substations, a dense footprint that spreads interconnection options across many points.

Wholesale activity over Nassau clears through the NYISO market (New York Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Nassau carries the state industrial average retail rate of 9.6 cents per kWh from EIA-861, applied statewide. For Nassau, the per-utility spread is 1 of 6 serving utilities: 26.0¢/kWh, which qualifies but never replaces the state average.

For Nassau, New York, no queued project appears in the feeds currently covered. In Nassau, 3 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Nassau shows 479.212 lb CO2 per MWh.

For Nassau, the USGS 2015 compilation records 205.35 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Nassau sits within commuting range of roughly 439,041 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Nassau here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Nassau, New York settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Nassau, New York requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Nassau, New York are logged directly below, so each figure on this page can be traced back to its public dataset.

Sources