Doña Ana, NM: data center power outlook
Doña Ana, New Mexico is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Doña Ana carries 23 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Doña Ana spans 4 utilities, with EL PASO ELECTRIC CO, OTERO COUNTY ELECTRIC COOP INC, RIO GRANDE ELECTRIC COOP, INC among those mapped.
Grid position at a glance
- Serving utilities
- EL PASO ELECTRIC CO, OTERO COUNTY ELECTRIC COOP INC, RIO GRANDE ELECTRIC COOP, INC, SIERRA ELECTRIC COOP, INC
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 345 kV
- Substations in county
- 23
- Industrial retail rate
- 5.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 4 serving utilities: 5.8 to 14.3¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- 305 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 1,011 lb CO2/MWh
- Water withdrawals
- 412 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 21,734 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Doña Ana
What follows is a screening-grade read of Doña Ana, New Mexico, built only from named public datasets. Grid access in Doña Ana extends to 345 kV, a high-voltage line class. The mapped layer packs 23 substations into Doña Ana, a dense spread of options.
Because Doña Ana, New Mexico sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For Doña Ana, the rate shown is the state industrial average of 5.9 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Doña Ana that report an industrial rate span 2 of 4 serving utilities: 5.8 to 14.3¢/kWh, shown as context and never as the county rate.
No interconnection-queue project is on record for Doña Ana, New Mexico in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. EIA-860M records 305 MW planned or under construction for Doña Ana. Doña Ana sits under a balancing authority that eGRID puts at 1,010.691 lb CO2 per MWh.
Doña Ana withdrew 411.78 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 21,734 people are employed in construction within a 120 km commute of Doña Ana (BLS QCEW), which frames staffing distance rather than free labour.
For Doña Ana, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Doña Ana, New Mexico describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Doña Ana, New Mexico, a specific address needs its own interconnection study, which this page does not attempt. The figures for Doña Ana, New Mexico refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.