The grid around Lander, Nevada is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Lander the mapped layer shows 7 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Lander is split among 2 utilities, among them SIERRA PACIFIC POWER CO, WELLS RURAL ELECTRIC CO.

Grid position at a glance

Serving utilities
SIERRA PACIFIC POWER CO, WELLS RURAL ELECTRIC CO
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
345 kV
Substations in county
7
Industrial retail rate
8.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
2 serving utilities: 4.9 to 5.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
14 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
705 lb CO2/MWh
Water withdrawals
157 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
20 employed in construction within ~120 km (1 of 2 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Lander

Read on for the public power picture of Lander in Nevada, assembled for data center siting. At 345 kV, Lander carries high-voltage transmission at its strongest mapped point. Lander contains 7 mapped substations, a moderate footprint spread across the service area.

No organized wholesale market covers Lander, Nevada, so capacity moves through the local utility and bilateral agreements. Lander carries the state industrial average retail rate of 8.1 cents per kWh from EIA-861, applied statewide. For Lander, the per-utility spread is 2 serving utilities: 4.9 to 5.2¢/kWh, which qualifies but never replaces the state average.

Lander, Nevada has nothing in the interconnection queue across the feeds covered here, quiet or uningested. In Lander, 14 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Lander shows 704.866 lb CO2 per MWh.

For Lander, the USGS 2015 compilation records 156.67 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Lander sits within commuting range of roughly 20 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Lander here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Lander, Nevada settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Lander, Nevada requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Lander, Nevada are logged directly below, so each figure on this page can be traced back to its public dataset.