Sherman, NE: data center power outlook

Sherman, Nebraska is served through the SPP market (Southwest Power Pool), and the figures below describe the public grid around a prospective data center site there. Sherman carries 4 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Sherman spans 6 utilities, with CUSTER PUBLIC POWER DISTRICT, DAWSON POWER DISTRICT, HOWARD GREELEY RURAL P P D among those mapped.

Grid position at a glance

Serving utilities
CUSTER PUBLIC POWER DISTRICT, DAWSON POWER DISTRICT, HOWARD GREELEY RURAL P P D, LOUP VALLEYS RURAL P P D, NEBRASKA PUBLIC POWER DISTRICT, WAPA-- WESTERN AREA POWER ADMINISTRATION
ISO / market
SPP (Southwest Power Pool)
Highest grid access
345 kV
Substations in county
4
Industrial retail rate
8.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 6 serving utilities: 4.5 to 13.0¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
872 lb CO2/MWh
Water withdrawals
70 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
7,010 employed in construction within ~120 km (16 of 22 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Sherman

What follows is a screening-grade read of Sherman, Nebraska, built only from named public datasets. Grid access in Sherman extends to 345 kV, a high-voltage line class. The mapped footprint in Sherman, Nebraska is sparse, 4 substations, so options cluster at those points.

Interconnection over Sherman runs through the SPP market (Southwest Power Pool) and its rules. For Sherman, the rate shown is the state industrial average of 8.0 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Sherman that report an industrial rate span 3 of 6 serving utilities: 4.5 to 13.0¢/kWh, shown as context and never as the county rate.

Across the covered feeds, Sherman, Nebraska carries no interconnection-queue project, from either real quiet or a feed not yet loaded. EIA-860M lists nothing planned or under construction for Sherman, Nebraska, which is a national filing and so a real zero. Sherman sits under a balancing authority that eGRID puts at 871.526 lb CO2 per MWh.

Sherman withdrew 69.78 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 7,010 people are employed in construction within a 120 km commute of Sherman (BLS QCEW), which frames staffing distance rather than free labour.

For Sherman, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Sherman, Nebraska describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Sherman, Nebraska, a specific address needs its own interconnection study, which this page does not attempt. The figures for Sherman, Nebraska refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.