Power by county
Johnson, NE: data center power outlook
Johnson, Nebraska is served through the SPP market (Southwest Power Pool), and the figures below describe the public grid around a prospective data center site there. Johnson carries 5 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Johnson spans 5 utilities, with CITY OF TECUMSEH, NEBRASKA PUBLIC POWER DISTRICT, NORRIS PUBLIC POWER DISTRICT among those mapped.
Grid position at a glance
- Serving utilities
- CITY OF TECUMSEH, NEBRASKA PUBLIC POWER DISTRICT, NORRIS PUBLIC POWER DISTRICT, OMAHA PUBLIC POWER DISTRICT, VILLAGE OF ELK CREEK - (NE)
- ISO / market
- SPP (Southwest Power Pool)
- Highest grid access
- 345 kV
- Substations in county
- 5
- Industrial retail rate
- 8.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 5 serving utilities: 4.5 to 7.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- 4 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 872 lb CO2/MWh
- Water withdrawals
- 16 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 45,422 employed in construction within ~120 km (28 of 30 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Johnson
What follows is a screening-grade read of Johnson, Nebraska, built only from named public datasets. Grid access in Johnson extends to 345 kV, a high-voltage line class. The mapped footprint in Johnson, Nebraska is sparse, 5 substations, so options cluster at those points.
Interconnection over Johnson runs through the SPP market (Southwest Power Pool) and its rules. For Johnson, the rate shown is the state industrial average of 8.0 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Johnson that report an industrial rate span 3 of 5 serving utilities: 4.5 to 7.2¢/kWh, shown as context and never as the county rate.
The covered queue feeds list nothing for Johnson, Nebraska, which may be quiet or simply uningested. EIA-860M records 4.2 MW planned or under construction for Johnson. Johnson sits under a balancing authority that eGRID puts at 871.526 lb CO2 per MWh.
Johnson withdrew 16.46 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 45,422 people are employed in construction within a 120 km commute of Johnson (BLS QCEW), which frames staffing distance rather than free labour.
For Johnson, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Johnson, Nebraska describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Johnson, Nebraska, a specific address needs its own interconnection study, which this page does not attempt. The figures for Johnson, Nebraska refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.