Clay, NE: data center power outlook

Clay, Nebraska is served through the SPP market (Southwest Power Pool), and the figures below describe the public grid around a prospective data center site there. Clay carries 19 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Clay spans 4 utilities, with CITY OF SUTTON - (NE), PERENNIAL PUBLIC POWER DIST, SOUTH CENTRAL PUBLIC PWR DIST among those mapped.

Grid position at a glance

Serving utilities
CITY OF SUTTON - (NE), PERENNIAL PUBLIC POWER DIST, SOUTH CENTRAL PUBLIC PWR DIST, SOUTHERN PUBLIC POWER DISTRICT
ISO / market
SPP (Southwest Power Pool)
Highest grid access
345 kV
Substations in county
19
Industrial retail rate
8.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 4 serving utilities: 6.4 to 11.6¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
872 lb CO2/MWh
Water withdrawals
125 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
19,062 employed in construction within ~120 km (24 of 28 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Clay

The material below frames Clay, Nebraska for a prospective large load, drawing only on public sources. Grid access in Clay extends to 345 kV, a high-voltage line class. The mapped layer places 19 substations across Clay, a moderate density.

Interconnection over Clay runs through the SPP market (Southwest Power Pool) and its rules. For Clay, the rate shown is the state industrial average of 8.0 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Clay that report an industrial rate span 3 of 4 serving utilities: 6.4 to 11.6¢/kWh, shown as context and never as the county rate.

Across the covered feeds, Clay, Nebraska carries no interconnection-queue project, from either real quiet or a feed not yet loaded. Nothing is on file for Clay, Nebraska in EIA-860M as planned or under construction, which counts as a measured zero. Clay sits under a balancing authority that eGRID puts at 871.526 lb CO2 per MWh.

Clay withdrew 125.45 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 19,062 people are employed in construction within a 120 km commute of Clay (BLS QCEW), which frames staffing distance rather than free labour.

For Clay, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Clay, Nebraska describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Clay, Nebraska, a specific address needs its own interconnection study, which this page does not attempt. The figures for Clay, Nebraska refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.