Power by county
Phillips, MT: data center power outlook
The grid around Phillips, Montana is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Phillips the mapped layer shows 11 mapped substations, with grid access reaching 230 kV at its strongest point. Retail service across Phillips is split among 6 utilities, among them BIG FLAT ELECTRIC COOP INC, FERGUS ELECTRIC COOP, INC, MCCONE ELECTRIC COOP INC.
Grid position at a glance
- Serving utilities
- BIG FLAT ELECTRIC COOP INC, FERGUS ELECTRIC COOP, INC, MCCONE ELECTRIC COOP INC, NORTHWESTERN ENERGY LLC - (MT), NORVAL ELECTRIC COOPERATIVE, INC, WAPA-- WESTERN AREA POWER ADMINISTRATION
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 230 kV
- Substations in county
- 11
- Industrial retail rate
- 7.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 6 serving utilities: 1.8 to 14.6¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 0 lb CO2/MWh
- Water withdrawals
- 317 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 221 employed in construction within ~120 km (3 of 4 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Phillips
Read on for the public power picture of Phillips in Montana, assembled for data center siting. Transmission-class access reaches 230 kV in Phillips at its strongest mapped point. Phillips contains 11 mapped substations, a moderate footprint spread across the service area.
No organized wholesale market covers Phillips, Montana, so capacity moves through the local utility and bilateral agreements. Phillips carries the state industrial average retail rate of 7.0 cents per kWh from EIA-861, applied statewide. For Phillips, the per-utility spread is 2 of 6 serving utilities: 1.8 to 14.6¢/kWh, which qualifies but never replaces the state average.
Phillips, Montana has nothing in the interconnection queue across the feeds covered here, quiet or uningested. The federal EIA-860M inventory files no planned or under-construction generation in Phillips, Montana, a real zero rather than a gap. In eGRID, the balancing authority over Phillips shows 0 lb CO2 per MWh.
For Phillips, the USGS 2015 compilation records 317.32 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Phillips sits within commuting range of roughly 221 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Phillips here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Phillips, Montana settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Phillips, Montana requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Phillips, Montana are logged directly below, so each figure on this page can be traced back to its public dataset.