Power by county

Putnam, MO: data center power outlook

Putnam, Missouri is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Putnam carries 6 mapped substations within its boundary, and the highest reachable grid access is 69 kV. Service in Putnam spans 7 utilities, with CHARITON VALLEY ELEC COOP, INC, CITY OF UNIONVILLE - (MO), GRUNDY ELECTRIC COOP, INC among those mapped.

Grid position at a glance

Serving utilities
CHARITON VALLEY ELEC COOP, INC, CITY OF UNIONVILLE - (MO), GRUNDY ELECTRIC COOP, INC, MACON ELECTRIC COOP, NORTH CENTRAL MO ELEC COOP INC, TRI-COUNTY ELECTRIC COOP ASSN (MO), UNION ELECTRIC CO - (MO)
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
69 kV
Substations in county
6
Industrial retail rate
8.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
2 of 7 serving utilities: 7.2 to 7.6¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
1 projects, 200 MW
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
1,285 lb CO2/MWh
Water withdrawals
2.0 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
6,248 employed in construction within ~120 km (27 of 33 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Putnam

What follows is a screening-grade read of Putnam, Missouri, built only from named public datasets. At 69 kV, the strongest mapped access in Putnam is sub-transmission class. The mapped layer places 6 substations across Putnam, a moderate density.

Sitting outside any organized market, Putnam, Missouri handles interconnection through its utility rather than a central operator. For Putnam, the rate shown is the state industrial average of 8.4 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Putnam that report an industrial rate span 2 of 7 serving utilities: 7.2 to 7.6¢/kWh, shown as context and never as the county rate.

The queue feeds show 1 project for Putnam, totalling 200 MW of requested capacity. EIA-860M lists nothing planned or under construction for Putnam, Missouri, which is a national filing and so a real zero. Putnam sits under a balancing authority that eGRID puts at 1,285.192 lb CO2 per MWh.

Putnam withdrew 2.02 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 6,248 people are employed in construction within a 120 km commute of Putnam (BLS QCEW), which frames staffing distance rather than free labour.

For Putnam, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Putnam, Missouri describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Putnam, Missouri, a specific address needs its own interconnection study, which this page does not attempt. The figures for Putnam, Missouri refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources