The grid around Phelps, Missouri is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Phelps the mapped layer shows 16 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Phelps is split among 8 utilities, among them CITY OF NEWBURG - (MO), CITY OF ROLLA - (MO), CITY OF SALEM - (MO).

Grid position at a glance

Serving utilities
CITY OF NEWBURG - (MO), CITY OF ROLLA - (MO), CITY OF SALEM - (MO), CITY OF ST JAMES - (MO), CRAWFORD ELECTRIC COOP, INC, GASCOSAGE ELECTRIC COOP, INTERCOUNTY ELECTRIC COOP ASSN, UNION ELECTRIC CO - (MO)
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
345 kV
Substations in county
16
Industrial retail rate
8.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
5 of 8 serving utilities: 6.9 to 8.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
1,285 lb CO2/MWh
Water withdrawals
9.6 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
20,486 employed in construction within ~120 km (24 of 27 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Phelps

The sections below set out what public data shows about siting a large electrical load in Phelps, Missouri. At 345 kV, Phelps carries high-voltage transmission at its strongest mapped point. Phelps contains 16 mapped substations, a moderate footprint spread across the service area.

No organized wholesale market covers Phelps, Missouri, so capacity moves through the local utility and bilateral agreements. Phelps carries the state industrial average retail rate of 8.4 cents per kWh from EIA-861, applied statewide. For Phelps, the per-utility spread is 5 of 8 serving utilities: 6.9 to 8.1¢/kWh, which qualifies but never replaces the state average.

Phelps, Missouri has nothing in the interconnection queue across the feeds covered here, quiet or uningested. For Phelps, Missouri, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Phelps shows 1,285.192 lb CO2 per MWh.

For Phelps, the USGS 2015 compilation records 9.64 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Phelps sits within commuting range of roughly 20,486 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Phelps here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Phelps, Missouri settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Phelps, Missouri requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Phelps, Missouri are logged directly below, so each figure on this page can be traced back to its public dataset.