Power by county
Mercer, MO: data center power outlook
The grid around Mercer, Missouri is summarized here from public data, starting from the county's position in the SPP market (Southwest Power Pool). Inside Mercer the mapped layer shows 6 mapped substations, with grid access reaching 69 kV at its strongest point. Retail service across Mercer is split among 5 utilities, among them EVERGY MISSOURI WEST, GRUNDY ELECTRIC COOP, INC, INTERSTATE POWER AND LIGHT CO.
Grid position at a glance
- Serving utilities
- EVERGY MISSOURI WEST, GRUNDY ELECTRIC COOP, INC, INTERSTATE POWER AND LIGHT CO, MACON ELECTRIC COOP, NORTH CENTRAL MO ELEC COOP INC
- ISO / market
- SPP (Southwest Power Pool)
- Highest grid access
- 69 kV
- Substations in county
- 6
- Industrial retail rate
- 8.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 5 serving utilities: 6.9 to 7.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 1,285 lb CO2/MWh
- Water withdrawals
- 2.3 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 7,088 employed in construction within ~120 km (29 of 35 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Mercer
Read on for the public power picture of Mercer in Missouri, assembled for data center siting. Grid access in Mercer peaks at 69 kV, below the transmission class most large loads look for. Mercer contains 6 mapped substations, a moderate footprint spread across the service area.
Wholesale activity over Mercer clears through the SPP market (Southwest Power Pool), whose footprint sets how interconnection requests and capacity are handled. Mercer carries the state industrial average retail rate of 8.4 cents per kWh from EIA-861, applied statewide. For Mercer, the per-utility spread is 2 of 5 serving utilities: 6.9 to 7.2¢/kWh, which qualifies but never replaces the state average.
Mercer, Missouri has nothing in the interconnection queue across the feeds covered here, quiet or uningested. No generation is filed as planned or under construction in Mercer, Missouri in the federal EIA-860M inventory, a measured zero rather than missing data. In eGRID, the balancing authority over Mercer shows 1,285.192 lb CO2 per MWh.
For Mercer, the USGS 2015 compilation records 2.27 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Mercer sits within commuting range of roughly 7,088 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Mercer here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Mercer, Missouri settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Mercer, Missouri requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Mercer, Missouri are logged directly below, so each figure on this page can be traced back to its public dataset.