Power by county
Greene, MO: data center power outlook
The grid around Greene, Missouri is summarized here from public data, starting from the county's position in the SPP market (Southwest Power Pool). Inside Greene the mapped layer shows 71 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Greene is split among 5 utilities, among them CITY UTILITIES OF SPRINGFIELD - (MO), OZARK ELECTRIC COOP INC - (MO), SOUTHWEST ELECTRIC COOP, INC.
Grid position at a glance
- Serving utilities
- CITY UTILITIES OF SPRINGFIELD - (MO), OZARK ELECTRIC COOP INC - (MO), SOUTHWEST ELECTRIC COOP, INC, WEBSTER ELECTRIC COOP, WHITE RIVER VALLEY EL COOP INC
- ISO / market
- SPP (Southwest Power Pool)
- Highest grid access
- 345 kV
- Substations in county
- 71
- Industrial retail rate
- 8.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 5 serving utilities: 8.0 to 9.5¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- 178 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 872 lb CO2/MWh
- Water withdrawals
- 100 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 20,945 employed in construction within ~120 km (26 of 27 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Greene
Read on for the public power picture of Greene in Missouri, assembled for data center siting. At 345 kV, Greene carries high-voltage transmission at its strongest mapped point. Greene contains 71 mapped substations, a dense footprint that spreads interconnection options across many points.
Wholesale activity over Greene clears through the SPP market (Southwest Power Pool), whose footprint sets how interconnection requests and capacity are handled. Greene carries the state industrial average retail rate of 8.4 cents per kWh from EIA-861, applied statewide. For Greene, the per-utility spread is 3 of 5 serving utilities: 8.0 to 9.5¢/kWh, which qualifies but never replaces the state average.
For Greene, Missouri, no queued project appears in the feeds currently covered. In Greene, 177.7 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Greene shows 871.526 lb CO2 per MWh.
For Greene, the USGS 2015 compilation records 99.71 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Greene sits within commuting range of roughly 20,945 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Greene here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Greene, Missouri settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Greene, Missouri requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Greene, Missouri are logged directly below, so each figure on this page can be traced back to its public dataset.