Greene, MS: data center power outlook

The grid around Greene, Mississippi is summarized here from public data, starting from the county's position in the MISO market (Midcontinent Independent System Operator). Inside Greene the mapped layer shows 17 mapped substations, with grid access reaching 230 kV at its strongest point. Retail service across Greene is split among 5 utilities, among them ALABAMA POWER CO, CLARKE-WASHINGTON E M C, DIXIE ELECTRIC POWER ASSN.

Grid position at a glance

Serving utilities
ALABAMA POWER CO, CLARKE-WASHINGTON E M C, DIXIE ELECTRIC POWER ASSN, MISSISSIPPI POWER CO, SINGING RIVER ELEC COOPERATIVE
ISO / market
MISO (Midcontinent Independent System Operator)
Highest grid access
230 kV
Substations in county
17
Industrial retail rate
7.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 5 serving utilities: 7.1 to 9.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
1 projects, 100 MW
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
843 lb CO2/MWh
Water withdrawals
2.6 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
32,242 employed in construction within ~120 km (19 of 21 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Greene

The sections below set out what public data shows about siting a large electrical load in Greene, Mississippi. Transmission-class access reaches 230 kV in Greene at its strongest mapped point. Greene contains 17 mapped substations, a moderate footprint spread across the service area.

Wholesale activity over Greene clears through the MISO market (Midcontinent Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Greene carries the state industrial average retail rate of 7.4 cents per kWh from EIA-861, applied statewide. For Greene, the per-utility spread is 3 of 5 serving utilities: 7.1 to 9.7¢/kWh, which qualifies but never replaces the state average.

Greene carries 1 project in the interconnection queue, totalling 100 MW of requested capacity. The federal EIA-860M inventory files no planned or under-construction generation in Greene, Mississippi, a real zero rather than a gap. In eGRID, the balancing authority over Greene shows 842.741 lb CO2 per MWh.

For Greene, the USGS 2015 compilation records 2.62 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Greene sits within commuting range of roughly 32,242 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Greene here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Greene, Mississippi settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Greene, Mississippi requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Greene, Mississippi are logged directly below, so each figure on this page can be traced back to its public dataset.