Power by county

Mackinac, MI: data center power outlook

Mackinac, Michigan is served through the MISO market (Midcontinent Independent System Operator), and the figures below describe the public grid around a prospective data center site there. Mackinac carries 21 mapped substations within its boundary, and the highest reachable grid access is 138 kV. Service in Mackinac spans 6 utilities, with ALGER-DELTA COOP ELECTRIC ASSN, CLOVERLAND ELECTRIC CO-OP, DTE ELECTRIC COMPANY among those mapped.

Grid position at a glance

Serving utilities
ALGER-DELTA COOP ELECTRIC ASSN, CLOVERLAND ELECTRIC CO-OP, DTE ELECTRIC COMPANY, PRESQUE ISLE ELEC & GAS COOP, UPPER MICHIGAN ENERGY RESOURCES CORP., UPPER PENINSULA POWER COMPANY
ISO / market
MISO (Midcontinent Independent System Operator)
Highest grid access
138 kV
Substations in county
21
Industrial retail rate
8.6¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
6 serving utilities: 5.3 to 12.6¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
1 projects, 160 MW
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
982 lb CO2/MWh
Water withdrawals
13 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
5,496 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Mackinac

What follows is a screening-grade read of Mackinac, Michigan, built only from named public datasets. At 138 kV, Mackinac sits in the transmission class that a large load would look to. The mapped layer packs 21 substations into Mackinac, a dense spread of options.

Interconnection over Mackinac runs through the MISO market (Midcontinent Independent System Operator) and its rules. For Mackinac, the rate shown is the state industrial average of 8.6 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Mackinac that report an industrial rate span 6 serving utilities: 5.3 to 12.6¢/kWh, shown as context and never as the county rate.

The queue feeds show 1 project for Mackinac, totalling 160 MW of requested capacity. Mackinac, Michigan has no EIA-860M generation on file, which reads as zero rather than as a gap. Mackinac sits under a balancing authority that eGRID puts at 981.982 lb CO2 per MWh.

Mackinac withdrew 12.66 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 5,496 people are employed in construction within a 120 km commute of Mackinac (BLS QCEW), which frames staffing distance rather than free labour.

For Mackinac, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Mackinac, Michigan describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Mackinac, Michigan, a specific address needs its own interconnection study, which this page does not attempt. The figures for Mackinac, Michigan refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources