Sabine, LA: data center power outlook
For Sabine, Louisiana, the public grid picture begins with its place in the SPP market (Southwest Power Pool) and the infrastructure mapped inside the county. Grid access across Sabine tops out at 500 kV, over a footprint of 11 mapped substations. In Sabine, 9 utilities share the retail territory, among them BEAUREGARD ELECTRIC COOP, INC, CLECO POWER LLC, DEEP EAST TEXAS ELEC COOP INC.
Grid position at a glance
- Serving utilities
- BEAUREGARD ELECTRIC COOP, INC, CLECO POWER LLC, DEEP EAST TEXAS ELEC COOP INC, ENTERGY LOUISIANA LLC, ENTERGY TEXAS INC., JASPER-NEWTON ELEC COOP, INC, RUSK COUNTY ELECTRIC COOP, INC, SOUTHWEST LOUISIANA E M C, SOUTHWESTERN ELECTRIC POWER CO
- ISO / market
- SPP (Southwest Power Pool)
- Highest grid access
- 500 kV
- Substations in county
- 11
- Industrial retail rate
- 6.2¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 5 of 9 serving utilities: 5.2 to 9.6¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 11 projects, 2,054 MW
- Proposed generation
- 220 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 3.6 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 11,828 employed in construction within ~120 km (18 of 20 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Sabine
This page gathers the public grid evidence for Sabine, Louisiana that bears on a large new load. The highest mapped voltage in Sabine is 500 kV, in the high-voltage transmission class. Sabine carries 11 substations in the mapped layer, spread across the county.
For Sabine, the SPP market (Southwest Power Pool) is the operator that handles interconnection and capacity. The state industrial average retail rate is 6.2 cents per kWh, drawn from EIA-861 and applied to Sabine at the state level rather than as a county rate. The serving utilities in Sabine that publish a rate range 5 of 9 serving utilities: 5.2 to 9.6¢/kWh, a spread kept separate from the state average.
On record for Sabine are 11 interconnection-queue projects, totalling 2,054 MW of requested capacity. Federal filings (EIA-860M) list 220 MW of generation as planned or under construction in Sabine. Grid carbon intensity for Sabine, via its balancing authority, is 981.982 lb CO2 per MWh in eGRID.
USGS 2015 puts freshwater withdrawals across Sabine at 3.58 million gallons per day for all uses, a measure of use, not spare supply. Within roughly a 120 km commute of Sabine, about 11,828 people are employed in construction (BLS QCEW), which speaks to how far crews for a multi-year build would travel, not to labour known to be free.
Read the Sabine figures as screening-grade context: they describe the surrounding grid, not a specific parcel. The numbers for Sabine, Louisiana qualify one another, so grid access, substation density, market membership, and rate are meant to be read as a set, not in isolation. Past this screening view, siting in Sabine, Louisiana turns on a study of a particular address, something no county-level page can stand in for. Every number shown for Sabine, Louisiana traces to a public source listed below, with its retrieval date, so the provenance is auditable rather than asserted.