Red River, LA: data center power outlook
For Red River, Louisiana, the public grid picture begins with its place in the SPP market (Southwest Power Pool) and the infrastructure mapped inside the county. Grid access across Red River tops out at 500 kV, over a footprint of 6 mapped substations. In Red River, 6 utilities share the retail territory, among them CLAIBORNE ELECTRIC COOP, INC, CLECO POWER LLC, ENTERGY LOUISIANA LLC.
Grid position at a glance
- Serving utilities
- CLAIBORNE ELECTRIC COOP, INC, CLECO POWER LLC, ENTERGY LOUISIANA LLC, PANOLA-HARRISON ELEC COOP, INC, SOUTHWEST LOUISIANA E M C, SOUTHWESTERN ELECTRIC POWER CO
- ISO / market
- SPP (Southwest Power Pool)
- Highest grid access
- 500 kV
- Substations in county
- 6
- Industrial retail rate
- 6.2¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 6 serving utilities: 5.2 to 11.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 4 projects, 620 MW
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 4.7 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 19,458 employed in construction within ~120 km (20 of 23 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Red River
For Red River, Louisiana, the following sections turn public grid records into a siting-oriented summary. The highest mapped voltage in Red River is 500 kV, in the high-voltage transmission class. Red River carries 6 substations in the mapped layer, spread across the county.
For Red River, the SPP market (Southwest Power Pool) is the operator that handles interconnection and capacity. The state industrial average retail rate is 6.2 cents per kWh, drawn from EIA-861 and applied to Red River at the state level rather than as a county rate. The serving utilities in Red River that publish a rate range 6 serving utilities: 5.2 to 11.1¢/kWh, a spread kept separate from the state average.
On record for Red River are 4 interconnection-queue projects, totalling 620 MW of requested capacity. For Red River, Louisiana, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. Grid carbon intensity for Red River, via its balancing authority, is 981.982 lb CO2 per MWh in eGRID.
USGS 2015 puts freshwater withdrawals across Red River at 4.68 million gallons per day for all uses, a measure of use, not spare supply. Within roughly a 120 km commute of Red River, about 19,458 people are employed in construction (BLS QCEW), which speaks to how far crews for a multi-year build would travel, not to labour known to be free.
Read the Red River figures as screening-grade context: they describe the surrounding grid, not a specific parcel. The numbers for Red River, Louisiana qualify one another, so grid access, substation density, market membership, and rate are meant to be read as a set, not in isolation. Past this screening view, siting in Red River, Louisiana turns on a study of a particular address, something no county-level page can stand in for. Every number shown for Red River, Louisiana traces to a public source listed below, with its retrieval date, so the provenance is auditable rather than asserted.