Evangeline, LA: data center power outlook

Evangeline, Louisiana is served through the MISO market (Midcontinent Independent System Operator), and the figures below describe the public grid around a prospective data center site there. Evangeline carries 9 mapped substations within its boundary, and the highest reachable grid access is 230 kV. Service in Evangeline spans 5 utilities, with BEAUREGARD ELECTRIC COOP, INC, CLECO POWER LLC, ENTERGY LOUISIANA LLC among those mapped.

Grid position at a glance

Serving utilities
BEAUREGARD ELECTRIC COOP, INC, CLECO POWER LLC, ENTERGY LOUISIANA LLC, POINTE COUPEE ELEC MEMBER CORP, SOUTHWEST LOUISIANA E M C
ISO / market
MISO (Midcontinent Independent System Operator)
Highest grid access
230 kV
Substations in county
9
Industrial retail rate
6.2¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
5 serving utilities: 5.2 to 11.3¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
12 projects, 1,565 MW
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
982 lb CO2/MWh
Water withdrawals
305 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
33,778 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Evangeline

The material below frames Evangeline, Louisiana for a prospective large load, drawing only on public sources. At 230 kV, Evangeline sits in the transmission class that a large load would look to. The mapped layer places 9 substations across Evangeline, a moderate density.

Interconnection over Evangeline runs through the MISO market (Midcontinent Independent System Operator) and its rules. For Evangeline, the rate shown is the state industrial average of 6.2 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Evangeline that report an industrial rate span 5 serving utilities: 5.2 to 11.3¢/kWh, shown as context and never as the county rate.

The queue feeds show 12 projects for Evangeline, totalling 1,565 MW of requested capacity. EIA-860M lists nothing planned or under construction for Evangeline, Louisiana, which is a national filing and so a real zero. Evangeline sits under a balancing authority that eGRID puts at 981.982 lb CO2 per MWh.

Evangeline withdrew 305.45 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 33,778 people are employed in construction within a 120 km commute of Evangeline (BLS QCEW), which frames staffing distance rather than free labour.

For Evangeline, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Evangeline, Louisiana describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Evangeline, Louisiana, a specific address needs its own interconnection study, which this page does not attempt. The figures for Evangeline, Louisiana refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.