Power by county
Taylor, KY: data center power outlook
The grid around Taylor, Kentucky is summarized here from public data, starting from the county's position in the PJM market (PJM Interconnection). Inside Taylor the mapped layer shows 13 mapped substations, with grid access reaching 161 kV at its strongest point. Retail service across Taylor is split among 5 utilities, among them EAST KENTUCKY POWER COOP, INC, INTER COUNTY ENERGY COOP CORP, KENTUCKY UTILITIES CO.
Grid position at a glance
- Serving utilities
- EAST KENTUCKY POWER COOP, INC, INTER COUNTY ENERGY COOP CORP, KENTUCKY UTILITIES CO, NOLIN RURAL ELECTRIC COOP CORP, TAYLOR COUNTY RURAL E C C
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 161 kV
- Substations in county
- 13
- Industrial retail rate
- 7.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 4 of 5 serving utilities: 5.5 to 7.5¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 5.9 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 63,583 employed in construction within ~120 km (42 of 52 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Taylor
Read on for the public power picture of Taylor in Kentucky, assembled for data center siting. Transmission-class access reaches 161 kV in Taylor at its strongest mapped point. Taylor contains 13 mapped substations, a moderate footprint spread across the service area.
Wholesale activity over Taylor clears through the PJM market (PJM Interconnection), whose footprint sets how interconnection requests and capacity are handled. Taylor carries the state industrial average retail rate of 7.0 cents per kWh from EIA-861, applied statewide. For Taylor, the per-utility spread is 4 of 5 serving utilities: 5.5 to 7.5¢/kWh, which qualifies but never replaces the state average.
Taylor, Kentucky has nothing in the interconnection queue across the feeds covered here, quiet or uningested. The federal EIA-860M inventory files no planned or under-construction generation in Taylor, Kentucky, a real zero rather than a gap. In eGRID, the balancing authority over Taylor shows 716.09 lb CO2 per MWh.
For Taylor, the USGS 2015 compilation records 5.89 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Taylor sits within commuting range of roughly 63,583 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Taylor here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Taylor, Kentucky settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Taylor, Kentucky requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Taylor, Kentucky are logged directly below, so each figure on this page can be traced back to its public dataset.