Power by county

Russell, KY: data center power outlook

Russell, Kentucky is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Russell carries 12 mapped substations within its boundary, and the highest reachable grid access is 161 kV. Service in Russell spans 5 utilities, with EAST KENTUCKY POWER COOP, INC, KENTUCKY UTILITIES CO, SOUTH KENTUCKY RURAL E C C among those mapped.

Grid position at a glance

Serving utilities
EAST KENTUCKY POWER COOP, INC, KENTUCKY UTILITIES CO, SOUTH KENTUCKY RURAL E C C, TAYLOR COUNTY RURAL E C C, TRI-COUNTY ELEC MEMBER CORP (TN)
ISO / market
PJM (PJM Interconnection)
Highest grid access
161 kV
Substations in county
12
Industrial retail rate
7.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 of 5 serving utilities: 5.5 to 9.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
21 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
18,288 employed in construction within ~120 km (36 of 48 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Russell

What follows is a screening-grade read of Russell, Kentucky, built only from named public datasets. At 161 kV, Russell sits in the transmission class that a large load would look to. The mapped layer places 12 substations across Russell, a moderate density.

Interconnection over Russell runs through the PJM market (PJM Interconnection) and its rules. For Russell, the rate shown is the state industrial average of 7.0 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Russell that report an industrial rate span 4 of 5 serving utilities: 5.5 to 9.7¢/kWh, shown as context and never as the county rate.

Across the covered feeds, Russell, Kentucky carries no interconnection-queue project, from either real quiet or a feed not yet loaded. Nothing is on file for Russell, Kentucky in EIA-860M as planned or under construction, which counts as a measured zero. Russell sits under a balancing authority that eGRID puts at 716.09 lb CO2 per MWh.

Russell withdrew 20.87 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 18,288 people are employed in construction within a 120 km commute of Russell (BLS QCEW), which frames staffing distance rather than free labour.

For Russell, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Russell, Kentucky describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Russell, Kentucky, a specific address needs its own interconnection study, which this page does not attempt. The figures for Russell, Kentucky refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources