Power by county
Powell, KY: data center power outlook
Powell, Kentucky is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Powell carries 11 mapped substations within its boundary, and the highest reachable grid access is 161 kV. Service in Powell spans 4 utilities, with CLARK ENERGY COOP INC - (KY), EAST KENTUCKY POWER COOP, INC, JACKSON ENERGY COOP CORP - (KY) among those mapped.
Grid position at a glance
- Serving utilities
- CLARK ENERGY COOP INC - (KY), EAST KENTUCKY POWER COOP, INC, JACKSON ENERGY COOP CORP - (KY), LICKING VALLEY RURAL E C C
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 161 kV
- Substations in county
- 11
- Industrial retail rate
- 7.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 4 serving utilities: 8.1 to 8.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 1.7 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 28,226 employed in construction within ~120 km (42 of 56 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Powell
The material below frames Powell, Kentucky for a prospective large load, drawing only on public sources. At 161 kV, Powell sits in the transmission class that a large load would look to. The mapped layer places 11 substations across Powell, a moderate density.
Interconnection over Powell runs through the PJM market (PJM Interconnection) and its rules. For Powell, the rate shown is the state industrial average of 7.0 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Powell that report an industrial rate span 3 of 4 serving utilities: 8.1 to 8.8¢/kWh, shown as context and never as the county rate.
The covered queue feeds list nothing for Powell, Kentucky, which may be quiet or simply uningested. Nothing is on file for Powell, Kentucky in EIA-860M as planned or under construction, which counts as a measured zero. Powell sits under a balancing authority that eGRID puts at 716.09 lb CO2 per MWh.
Powell withdrew 1.65 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 28,226 people are employed in construction within a 120 km commute of Powell (BLS QCEW), which frames staffing distance rather than free labour.
For Powell, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Powell, Kentucky describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Powell, Kentucky, a specific address needs its own interconnection study, which this page does not attempt. The figures for Powell, Kentucky refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.