Power by county

Laurel, KY: data center power outlook

The grid around Laurel, Kentucky is summarized here from public data, starting from the county's position in the PJM market (PJM Interconnection). Inside Laurel the mapped layer shows 31 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Laurel is split among 6 utilities, among them CORBIN CITY UTILITIES COMM, CUMBERLAND VALLEY ELECTRIC, INC., EAST KENTUCKY POWER COOP, INC.

Grid position at a glance

Serving utilities
CORBIN CITY UTILITIES COMM, CUMBERLAND VALLEY ELECTRIC, INC., EAST KENTUCKY POWER COOP, INC, JACKSON ENERGY COOP CORP - (KY), KENTUCKY UTILITIES CO, SOUTH KENTUCKY RURAL E C C
ISO / market
PJM (PJM Interconnection)
Highest grid access
345 kV
Substations in county
31
Industrial retail rate
7.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 of 6 serving utilities: 7.1 to 9.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
9.5 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
27,414 employed in construction within ~120 km (41 of 52 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Laurel

The sections below set out what public data shows about siting a large electrical load in Laurel, Kentucky. At 345 kV, Laurel carries high-voltage transmission at its strongest mapped point. Laurel contains 31 mapped substations, a dense footprint that spreads interconnection options across many points.

Wholesale activity over Laurel clears through the PJM market (PJM Interconnection), whose footprint sets how interconnection requests and capacity are handled. Laurel carries the state industrial average retail rate of 7.0 cents per kWh from EIA-861, applied statewide. For Laurel, the per-utility spread is 4 of 6 serving utilities: 7.1 to 9.7¢/kWh, which qualifies but never replaces the state average.

For Laurel, Kentucky, no queued project appears in the feeds currently covered. For Laurel, Kentucky, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Laurel shows 716.09 lb CO2 per MWh.

For Laurel, the USGS 2015 compilation records 9.47 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Laurel sits within commuting range of roughly 27,414 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Laurel here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Laurel, Kentucky settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Laurel, Kentucky requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Laurel, Kentucky are logged directly below, so each figure on this page can be traced back to its public dataset.

Sources