Power by county

Grant, KY: data center power outlook

Grant, Kentucky is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Grant carries 7 mapped substations within its boundary, and the highest reachable grid access is 765 kV. Service in Grant spans 6 utilities, with BLUE GRASS ENERGY COOP CORP, DUKE ENERGY KENTUCKY, EAST KENTUCKY POWER COOP, INC among those mapped.

Grid position at a glance

Serving utilities
BLUE GRASS ENERGY COOP CORP, DUKE ENERGY KENTUCKY, EAST KENTUCKY POWER COOP, INC, KENTUCKY UTILITIES CO, OWEN ELECTRIC COOP INC, WILLIAMSTOWN UTILITY COMM
ISO / market
PJM (PJM Interconnection)
Highest grid access
765 kV
Substations in county
7
Industrial retail rate
7.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 of 6 serving utilities: 6.1 to 9.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
No eGRID rate published for this balancing authority
Water withdrawals
2.1 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
106,793 employed in construction within ~120 km (47 of 59 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Grant

The material below frames Grant, Kentucky for a prospective large load, drawing only on public sources. Grid access in Grant extends to 765 kV, the extra-high-voltage class. The mapped layer places 7 substations across Grant, a moderate density.

Interconnection over Grant runs through the PJM market (PJM Interconnection) and its rules. For Grant, the rate shown is the state industrial average of 7.0 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Grant that report an industrial rate span 4 of 6 serving utilities: 6.1 to 9.8¢/kWh, shown as context and never as the county rate.

No interconnection-queue project is on record for Grant, Kentucky in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. Nothing is on file for Grant, Kentucky in EIA-860M as planned or under construction, which counts as a measured zero. For Grant, Kentucky, eGRID rates no output for the covering balancing authority, and the carbon field stays empty.

Grant withdrew 2.14 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 106,793 people are employed in construction within a 120 km commute of Grant (BLS QCEW), which frames staffing distance rather than free labour.

For Grant, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Grant, Kentucky describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Grant, Kentucky, a specific address needs its own interconnection study, which this page does not attempt. The figures for Grant, Kentucky refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources