The grid around Posey, Indiana is summarized here from public data, starting from the county's position in the MISO market (Midcontinent Independent System Operator). Inside Posey the mapped layer shows 38 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Posey is split among 8 utilities, among them AMEREN ILLINOIS COMPANY, DUKE ENERGY INDIANA, LLC, KENERGY CORP.

Grid position at a glance

Serving utilities
AMEREN ILLINOIS COMPANY, DUKE ENERGY INDIANA, LLC, KENERGY CORP, KENTUCKY UTILITIES CO, SOUTHEASTERN IL ELEC COOP, INC, SOUTHERN INDIANA GAS & ELEC CO, WAYNE-WHITE COUNTIES ELEC COOP, WESTERN INDIANA ENERGY REMC
ISO / market
MISO (Midcontinent Independent System Operator)
Highest grid access
345 kV
Substations in county
38
Industrial retail rate
8.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 8 serving utilities: 7.9 to 10.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
12 projects, 2,691 MW
Proposed generation
250 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
982 lb CO2/MWh
Water withdrawals
19 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
25,525 employed in construction within ~120 km (39 of 43 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Posey

Read on for the public power picture of Posey in Indiana, assembled for data center siting. At 345 kV, Posey carries high-voltage transmission at its strongest mapped point. Posey contains 38 mapped substations, a dense footprint that spreads interconnection options across many points.

Wholesale activity over Posey clears through the MISO market (Midcontinent Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Posey carries the state industrial average retail rate of 8.9 cents per kWh from EIA-861, applied statewide. For Posey, the per-utility spread is 3 of 8 serving utilities: 7.9 to 10.4¢/kWh, which qualifies but never replaces the state average.

Posey carries 12 projects in the interconnection queue, totalling 2,691 MW of requested capacity. In Posey, 250 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Posey shows 981.982 lb CO2 per MWh.

For Posey, the USGS 2015 compilation records 18.74 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Posey sits within commuting range of roughly 25,525 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Posey here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Posey, Indiana settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Posey, Indiana requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Posey, Indiana are logged directly below, so each figure on this page can be traced back to its public dataset.