Power by county
Pike, IN: data center power outlook
The grid around Pike, Indiana is summarized here from public data, starting from the county's position in the MISO market (Midcontinent Independent System Operator). Inside Pike the mapped layer shows 20 mapped substations, with grid access reaching 765 kV at its strongest point. Retail service across Pike is split among 6 utilities, among them AGC DIVISION OF APGI INC, DAVIESS MARTIN COUNTY R E M C, DUBOIS RURAL ELECTRIC COOP INC.
Grid position at a glance
- Serving utilities
- AGC DIVISION OF APGI INC, DAVIESS MARTIN COUNTY R E M C, DUBOIS RURAL ELECTRIC COOP INC, DUKE ENERGY INDIANA, LLC, SOUTHERN INDIANA GAS & ELEC CO, WESTERN INDIANA ENERGY REMC
- ISO / market
- MISO (Midcontinent Independent System Operator)
- Highest grid access
- 765 kV
- Substations in county
- 20
- Industrial retail rate
- 8.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 6 serving utilities: 6.0 to 10.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 16 projects, 2,151 MW
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 376 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 32,964 employed in construction within ~120 km (43 of 45 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Pike
The sections below set out what public data shows about siting a large electrical load in Pike, Indiana. At 765 kV, Pike carries extra-high-voltage transmission at its strongest mapped point. Pike contains 20 mapped substations, a moderate footprint spread across the service area.
Wholesale activity over Pike clears through the MISO market (Midcontinent Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Pike carries the state industrial average retail rate of 8.9 cents per kWh from EIA-861, applied statewide. For Pike, the per-utility spread is 6 serving utilities: 6.0 to 10.4¢/kWh, which qualifies but never replaces the state average.
Pike carries 16 projects in the interconnection queue, totalling 2,150.5 MW of requested capacity. For Pike, Indiana, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Pike shows 981.982 lb CO2 per MWh.
For Pike, the USGS 2015 compilation records 375.9 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Pike sits within commuting range of roughly 32,964 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Pike here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Pike, Indiana settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Pike, Indiana requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Pike, Indiana are logged directly below, so each figure on this page can be traced back to its public dataset.