Noble, IN: data center power outlook
Noble, Indiana is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Noble carries 23 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Noble spans 8 utilities, with INDIANA MICHIGAN POWER CO, LAGRANGE COUNTY RURAL E M C, MIDWEST ENERGY COOPERATIVE among those mapped.
Grid position at a glance
- Serving utilities
- INDIANA MICHIGAN POWER CO, LAGRANGE COUNTY RURAL E M C, MIDWEST ENERGY COOPERATIVE, NOBLE COUNTY R E M C, NORTHEASTERN RURAL E M C, NORTHERN INDIANA PUB SERV CO, PAULDING-PUTMAN ELEC COOP, INC, TOWN OF AVILLA - (IN)
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 345 kV
- Substations in county
- 23
- Industrial retail rate
- 8.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 5 of 8 serving utilities: 4.6 to 16.3¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 9.0 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 57,294 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Noble
What follows is a screening-grade read of Noble, Indiana, built only from named public datasets. Grid access in Noble extends to 345 kV, a high-voltage line class. The mapped layer packs 23 substations into Noble, a dense spread of options.
Interconnection over Noble runs through the PJM market (PJM Interconnection) and its rules. For Noble, the rate shown is the state industrial average of 8.9 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Noble that report an industrial rate span 5 of 8 serving utilities: 4.6 to 16.3¢/kWh, shown as context and never as the county rate.
The covered queue feeds list nothing for Noble, Indiana, which may be quiet or simply uningested. Nothing is on file for Noble, Indiana in EIA-860M as planned or under construction, which counts as a measured zero. Noble sits under a balancing authority that eGRID puts at 716.09 lb CO2 per MWh.
Noble withdrew 9.04 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 57,294 people are employed in construction within a 120 km commute of Noble (BLS QCEW), which frames staffing distance rather than free labour.
For Noble, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Noble, Indiana describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Noble, Indiana, a specific address needs its own interconnection study, which this page does not attempt. The figures for Noble, Indiana refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.